Enhancing the safety, reliability and resilience of the scour system and upgrading the emergency draw-off system, enabling remote operation.
Glenfield Invicta replaced the existing bulkhead gate and primary gate as well as supplying a new secondary gate. The project was classified ‘gold command’ due to single point of isolation during repair works. The existing bulkhead gate was holding back 250 tons of water.
Background
The gates were designed, manufactured and installed by Glenfield Invicta, in conjunction with our sister company Orbinox. In addition, our engineering support included the provision of Computational Fluid Dynamics (CFD) analysis to ensure increased effectiveness of the design and to ensure the risk of cavitation was reduced.
Unique Challenges
The tower itself was situated in the middle of the reservoir and all works had to be carried out whilst the reservoir remained fully operational. This involved a high level of risk and had to be carefully managed and coordinated.
Solution
Bespoke large fabricated bulkhead and roller gates
Specification
• Hydraulically Operated
• Stainless Steel
Size
• Secondary Gate = 1800mm x 2550mm
• Primary Gate = 2000mm x 2550mm
• Bulkhead Gate = 2800mm x 3900mm